Precautions for installation of Indian hydraulic baler
Release time: 2021-12-28 sentiment:1060 time
Precautions for installation of hydraulic baler:
1. Some parts of the waste paper hydraulic baler are packed in boxes and some parts are bundled for transportation. After receiving the goods, the user must carefully check the packing list to avoid loss during transportation.
2. The foundation construction must be carried out in accordance with the foundation plan and leveled with a spirit level.
3. The dirt must be cleaned up before the machine is installed. If the surface of the parts is corroded, it should be cleaned with kerosene.
4. Hoist the host after the foundation is solidified.
5. When installing the hydraulic control system, the joints should be filled with "O" seals to avoid oil leakage.
6. Install the main pump valve oil circuit, all pipes must be cleaned, and the oil pump station is placed and leveled. Clean the inside of the fuel tank to remove the dirt that enters during transportation, and tie it with a hose clamp to prevent oil leakage caused by vibration.
7. According to the electrical schematic diagram, install all the lines to ensure the safe operation of the hydraulic baler.
The above is the installation of hydraulic baler shared by Nick Machinery. For more details, please visit www.nkbalers.com